Kalba: 400MW on paper. Power decides.

2 min read Igor Filippov

On 19 November 2026, Sharjah’s Deputy Ruler approved the master plan for the Communications Technology Free Zone in Kalba, on the emirate’s east coast. The zone itself was created by decree in July 2024. Now it has a physical plan.

What was announced

The site covers 285,000 square metres, about three kilometres from the Gulf of Oman. The target data centre capacity is 400MW. The plan includes six plots that can be combined into larger campuses, and land reserved for two power stations.

Why the location matters

Kalba faces the open Gulf of Oman, outside the Strait of Hormuz. My reflection: for subsea cable landings and route diversity, an east coast site could give the UAE a useful second coastline for digital infrastructure. Whether that happens depends on which cable systems actually land there.

What decides the project

Power. A 400MW target on a master plan is a statement of intent, not a power commitment. Before a serious developer or investor takes a plot, they will want clear answers to four questions:

  1. Who builds and operates the two power stations?
  2. What sits behind them: gas, grid supply, solar with storage, or a mix?
  3. What is the interconnection timeline, phase by phase?
  4. Who pays for the upgrades, and how is that reflected in the plot price?

What is still unknown

No operator, anchor tenant, construction date or budget has been announced. That is normal at the master plan stage. The next useful signal will be a written power allocation with milestones, followed by the first anchor tenant.

Our view

Kalba has the right geography. Whether it becomes a real 400MW campus depends on how fast power moves from the plan to signed contracts. We will keep watching for that step.